Hi experts,

Do you know if there´s one Sap transaction to see budget forecast ? For example, I would like to see the costs forecast for equipaments based on past plans and work orders ?

Thanks,

Cabral.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 27, 2012 at 06:34 AM

    hi

    Try Below T.codes.

    FMRP_RW_BUDCON - Budget Consumption Report Logistics Execution - Information system

    IM52 - Process budget distribution Investment Management - Investment Programs

    OPS9 - Budget Management Profile Project Systems - Project System

    FMB_PT01 - Budget Totals Vs. Commt./Actual Tot. FI - Budgeting

    FMRP_RW_BUDGET - Budget Report SD - Information system

    KOAB - Order Types: Budget Profile CO - Overhead Cost Orders

    CJ37 - Budget Supplement in Project CO - Cost Planning in the WBS

    CJ36 - Budget Supplement to Project CO - Cost Planning in the WBS

    CJ38 - Budget Return in Project CO - Cost Planning in the WBS

    IM32 - Change Budget of Inv. Prog. Position Investment Management - Investment Programs

    CJ34 - Project Budget Transfer CO - Cost Planning in the WBS

    FM9K - FIFM: Change Budget Structure PP - Budgeting and Availability Control

    FMBOSTAT - Maintain budget object & status CO - Budgeting

    FMCYLOAD - Copy budget data (load) FI - Budgeting

    CJ35 - Budget Return from Project CO - Cost Planning in the WBS

    KOCO - Budget Carryforward for Orders FI - Funds Management

    OF20 - FM Budget Avail.Control Tolerances Logistics - Budgeting and Availability Control

    FMIC - Generate Additional Budget Incr.Data FI - Budgeting and Availability Control

    FMG2 - Change Budget Structure Template Real Estat - Budgeting and Availability Control

    FMB_B02 - Budget View by Process Cross Application - Budgeting

    CJI8 - Project Budget Line Items Project Systems - Accounting

    CJ3A - Change Budget Document CO - Cost Planning in the WBS

    OPI6 - Activate CO Cash Budget Management Project Systems - Actual Payments and Forecast

    FM9P - Reconstruct Budget Distrbtd Values MM - Budgeting and Availability Control

    IM53 - Display budget distribution Investment Management - Investment Programs

    Add comment