Activity Creation Date - Table

Former Member
0 Kudos

Hi PS Gurus

We are creating Project Structure in CJ20N

The following is hierechial structure

Project --> WBS ---> Network -


> Activity -


> Person assignment

I need to know , where Activity Creation date is stored

I have checked Table AFVC , AFVV , AFVU , but nowhere this info has been found

rgds

sandeep

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

> I need to know , where Activity Creation date is stored

Hi please check in activity under administration tab.

I doubt Activity has got Admin. Tab. Please activate change document for network header and try whether you can get the activity creation date as a change date for network header from the change document tables.

hemu_katta
Participant
0 Kudos

Hi please check in activity under administration tab. you will find it.

thank you