Material assignment & Budget checking

Dear PS experts,

Project created - Project definition, WBS elements, Network & activity. Budget assigned.

While assigning material (Item category - L, MRP 4 - Ind/Coll indicator - blank)

1. Project created status

a) If I select Procurement indicator "Reservation for network", it's showing "error in commitment check" if material value is more than the budget.

b) If I select Procurement indicator "P.Req + Reservation for WBS element", it's NOT showing any error for the same material & quantity and I am able to trigger purchase requisition from project.

2. Project released status

It's showing "error in commitment check" for both a & b.

Please help me to resolve this.

Thanks & Regards,

Murthy.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 25, 2012 at 11:19 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 25, 2012 at 10:15 AM

    Hi,

    Please check if any user status is maintain for your project. May be in CRTD availability check is restricted and from REL system is checking for the availability.

    Alos check in tolerence limit setting all transcation (++) setting is maintained.

    regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Thank you for your response.

      I have not maintained any user status and Transaction group ++ is maintained.

      Regards,

      Murthy.