on 01-25-2012 7:03 AM
Dear Sir,
I have G/L Account wise company budget.
I want to compare the same with G/L actual balance and arrive at a variance report.
While executing the financial report at F.01 if I select Plan version as 0
the report is displaying the actual figure and at planned column it is not showing any amount.
I understand that this is because I have not yet maintained any amount in Planed version.
I want to know How to maintain G/L account wise planned amount that can be compared while executing F.01?
or
is there any other means by which my above referred objective can be achieved?
Regards
Chirag Shah
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please refere the below link.
[Entering Plan Data|http://help.sap.com/saphelp_dimp50/helpdata/en/27/94fa40fe14f423e10000000a155106/content.htm]
Tcode: FSE5N
Regards,
Srinu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.