What is the Exact differences between Earliest and Latest Dates??

HI All,

I am learning the SAP PS course and asking basic questions which i got during my preparation....Please Clarify my basic questions...

Thanks A Bunch

sappstrainee

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Jan 25, 2012 at 04:23 AM

    Hi...

    a Few m ore questions..

    0. What are the Significances of WBS and NTW??

    1. Exact differences between Activity and activity element?

    2. Date planning with only WBS elements in a project??

    3. Scheduling with WBS and NtW in a project??

    4. Limitations of User Status ??

    5. What is User Exit??

    6. What is Status Function??

    7. what is warehouse Stock,Project Stock,Sales order Stock and differences??

    8. Types of Reporting??(hierarchy,costelement,lineitem)

    9.What is Subcontracting??

    10. What is Subnetwork Monitor??

    11. What is material order??

    12. Diff btn Structure Information System and Control information System??

    13. What is In- House Production Cycle??External Procurement Cycle??

    please don't hesitate for these basic questions also don't consider this as an interview to you...

    Thanks

    sappstrainee

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      For all your basic queries please refer SAP Help. Assuming that you are taking the PS course from an authorized institute i would suggest you to ask your doubts to the trainer.

      Basic queries are rarely answered in this forum. The best place to clarify your doubts is through SAP Help.

  • avatar image
    Former Member
    Jan 25, 2012 at 06:20 PM

    Hi

    If you know the what is scheduling then you would certainly understand.

    Any have as Gokul already pointed out, please read help and other serach engines to lear more about PS basics.

    All the best.

    Regards,

    PSR

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 27, 2012 at 10:11 AM

    I am not against other people's posts, but to clarify you and to my knowledge:

    Earliest date (Start or Finish): refers to how soon an activity can Start or Finish per your schedule

    Latest date (Start or Finish): refers to how late an activity can Start or Finish per your schedule

    And, as others suggested, you need to refer to baiscs of scheduling to understand on how scheduling works in SAP. Forward/Backward pass, Critical path, TF (Total Float) & FF (Free Float), Lead-Lag relations are few other essential things to know.

    Try this:

    http://pmbook.ce.cmu.edu/10_fundamental_scheduling_procedures.html

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 30, 2012 at 10:40 AM

    Hi,

    Earliest Dates:

    I give a start date of the project (or network) to let the program calculate wann a certatin activity will start using that start date.

    => Forward scheduling determine the earliest date2.

    Latest Dates:

    I known that deadline of the project (or network), I use this finish date to let program to calculate wann a certain activity need to be finished to fullfil the deadline.

    => Backward scheduling determine the latest dates.

    If the latest dates of an activity is earlier than the earliest dates, =>negative float, so either you should start the project (or network) more earlier, or you need postphone the deadline.

    => see consulting note 151551 about scheduling topic.

    Kind regards,

    Zhenbo