In a 3rd party sales scenario, order status becomes complete even when it is partially invoiced. for example order qty is 4, PR created for 4 qty, PO created for 4 qty, MIRO is done for 2 qty, Customer Invoice is done for 2 qty. At this situation, the order status goes to complete. When I do a MIRO for the remaining 2 qty, the order status becomes being processed and when I create invoice for the remaining 2 qty, the status becomes complete.

Question here is, is there a way to prevent the order from getting into complete status before it is fully invoiced?

Let me know guys.

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Jan 25, 2012 at 09:45 AM

    Hi,

    You cannot achieve this using standard customizing, as for thord party the billing quanity is always proposed against MIRO and the logic is that after partial delivery/invoicing by supplier, the sales order becomes completed. If you expect partial deliveries )or you have planned them with the supplier), you need to split the sales order qty into separate items according to the actual delivery date by the supplier.

    Regards,

    Marcin

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 24, 2012 at 02:40 PM

    Hi Vasanth,

    You can achieve this by setting the billing relevance as B for item category in question.

    But before doing this please consider all pros and cons of this.

    Hope this will help you.

    Thanks and Regards,

    Atulkumar Dagade

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 24, 2012 at 02:47 PM

    As mentioned in one of your earlier threads, maintain billing relevance as F and then check again.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 06, 2012 at 01:12 PM

    Thanks for the feedback

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.