Billing before cost estimated released.

40 Views

Dears,

Cost estimated for a given material was marked and released on 04.01.2011 but the first billing document was posted on 03.01.2011 so the system displays an error saying that there is no cost estimated for this date. My question is which date should be changed on the billing document? The billing date or the delivery date or any other date? As i could check there is no way to perform a new cost estimate"CK11N" for a past date.

Thanks in Advance,

Regards.