LTP Run...

21 Views

I have create a planning scenario and put here receptive inactive version on that scenario. Requirement is there on that inactive version for those material. That can i see in MD61. So when I will run LTP by MS02, then no requirement will be calculated. Also when I have checked in MS04 , there are no planned order for requirement, only showing the opening stock.

Plz give me the solution how to run LTP with planning scenario with particular material and plant.