BADI GCC_PS_PROJECT_LABEL-->GET_WBS_ELEMENT

54 Views

Hi,

We are using the standard business key 'CPROJECTS' and the standard implementation of the badi GCC_PS_PROJECT_LABEL. We have both cProjects and PS in the same instance.

I have observed that the badi is not being called when creating the PS Project from cProject.

In the controlling scenario we are using roles of cProject for creating the WBS element and the transfer type in Project is Flag for Transfer. Please suggest me how to call the badi so that the WBS ID can be changed during creation time.

Thanks in Advance,

Priyatham