MD01 prameters

Hi,

My client's process is MTO. Only for last level raw materials it is MTS. So I have used strategy 20 for finished and semi finished.

Client says after sales orders are created in system and MRP run is done, still quantity of sales orders may be changed ( increased or decreased) if their customers say so.I have suggested client to run MRP in background in MD01. But I just want to know what should be setting for Processing key and Planning mode in such case of sales order's qty change?

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2012 at 05:37 AM

    processing key = NETPL or NETCH

    planning mode = 1

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi DB,

      Thanks a tonne! You have always helped us a lot.There was some problem in my internet connection hence there was a delay in response!

      Just one more clarifications before I close this thread:

      Pls explain what do you mean by 'If you find yourself doing this a lot, you can re-position the 'req closed' button so as to be immediately visible during conversion, using standard table display variants within ME22N.' What is standard display variants??

      I am really surprised that in case of sales order qty reduction, then user has to manully change qty of production order or firmed planned orders at all semi finished levels!! Imagine if there are many levels of BoM and so many Stock transport PR/PO's involved, then it is a tedious and herculean task!!

      Regards.

  • Posted on Jan 23, 2012 at 05:51 AM

    You can use the following settings,

    Processing key                  NETCH
    Create purchase req.            1
    Schedule lines                  3
    Create MRP list                 1
    Planning mode                   1
    Scheduling                      1
    

    Additional information: You'd have to separate out some materials which are more frequently ordered during the day like consumption based planning materials by using user exit and run MRP more frequently like every 15 mins or an hour (in a separate job), in that case just set "create MRP list" = 3 so that it won't hog sap system.

    You can read the following you're interested in userexit

    Edited by: Jeevan Sagar on Jan 23, 2012 1:02 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 23, 2012 at 06:41 AM

    Since your order quantities gets changed frequently, i will suggest the following indicators

    Processing key: NETCH

    Create purchase req: 1

    Schedule lines: 3

    Create MRP list: 1

    Planning mode: 3 Delete and recreate planning data

    Thanks

    Hrishi

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2012 at 10:02 AM

    Dear me_sappp

    As per harish

    Processing key: NETCH

    Create purchase req: 1 Purchase requisitions

    Schedule lines: 3 Schedule lines

    Create MRP list: 1 MRP list

    Planning mode: 3 Delete and recreate planning data

    Thanks

    Alok Mohapatra

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 23, 2012 at 10:47 AM

    Hi,

    As other users said maintain the following parameters....

    Processing key - NETCH

    Create purchase req - 3 (planned orders)

    Schedule lines - 3

    Create MRP list - 1

    Planning mode - 1

    Scheduling - 2 , this will calculate the schedule dates in the planned order based on routing times.

    Thanks,

    Ravi

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 24, 2012 at 05:03 AM

    Hi,

    Use like this.

    Processing key: NETCH

    Create purchase req: 3(Planned order)

    Schedule lines: 3

    Create MRP list: 1

    Planning mode:1

    What I understant your customer requirement is finished product level MTO and below thst MTS. You can use startegy 50. Here final assembly will only triggered after the sales order has received. Below the finished product you can produce the material for stock. This will reduce the dekivery lead time and quantity change in sales order will be considered also.

    Regards,

    Krishnendu

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.