Hi Experts,
We are using the project system to collate order costs for annual shut work. We have a requirement for a report to show 25% variance between planned and actual order costs (maintneance order).
At this stage, we dont mind whether this is implemented in the the PM system, or the PS system.
This is a fairly basic / common requirment. Are there any standard transactions we could use to:
1. Select a list of orders using standard selection criteria.
2. Select a % for variance, e.g. 25%
3. Display a list of orders where the planned vs actual costs were greater than 25% and what the actual variance is for each order?
Thanks,
Maikel