I have a knowledge question regarding collective entry of confirmations using repetitive manufacturing u2013 transaction MF42N.

Is there an option to get data from planning table (MF50) pre-selected to simplify final backflushing such as:

Preselect all planned orders (PE) of a defined plant for a pre-selected planned production date or all materials with planned orders for a defined planned production date shall be pre-selected.

I donu2019t see an option to preselect open planned orders for backflushing .

I only see the option to manually enter either material or planned order for each single planned quantity from planning table.

It is vital for the central kitchen food production process to be as simple as possible.

Whatever can be pre-selected improves usability of this process for Retailers significantly.

rgds