This is the SAP standard situation
You cannot deliver materials that are defined as assembly items (negative requirement quantity). If you want to deliver components that are assembled in a network, you must allocate them to a subsequent activity with positive requirements quantities and deliver them from this activity.
My question
Now my question do this issue, it isnu2019t very useful to go and change manually the negative to the positive requirements at the network. Is there any exit or other possibility which give us a better solution?
We do our work process with the CN33.
Thank you for any god idea and sollutions.
Kind regards
Beat