Former Member
Jan 20, 2012 at 03:56 PM

Settlement rule in rework process order

85 Views

Hello

When creating a rework process order without material in CORO the system is asking automatically for the settlement rules. Here we can then maintain a cost center order order. This is very nice and perfectly fine to us.

When now creating in a different case a rework order with material in COR1 (because we plan a goods receipt) the system is automatically taking the material as default settlement rule without asking the user. Would anybody know a way how to customize the system to ask the user in any case for the settlement rules? So the user really has to make a choice and is not always forgetting to update the correct values which are not only the material. (kind of a training issue but maybe the system can do something about that..)

Thanks