Folks-
Have an MRP Question hope someone can help!
We have an MRP run for a material in SAP that triggered a fill to max PO today. However, there is already a PO that is scheduled to be delivered 3 months later. Would you be able to tell me why that is?
Under Forecast requirement, its set to Monthly
Rescheduling Horizon is set to 0 with No impact to PO/SA (ie unchecked)
Regards
Edited by: Rahul Bhutani on Jan 19, 2012 9:32 AM