Planned Delivery time in Extl Processing/Sub contarcating PO in Prod order

118 Views

Hi All ,

I have External processing Operation in my routing and i have maintained the control key as PP02 and Mainatined the Plannned Deliver time for that operation , But when i do production order scheduling system is not considering the Planned Delivery time , How to make the system to consider the Planned Delivery time in production Order scheduling .

Example :\

production order:0001

Operation 0010 - Internal (Control Key -PP01) 4 HRS

operation 0020 internal (Control Key -PP01) - 4 HRS

operation 0030 External((Control Key -PP02) 10 DAYS

Operation 0040 --- Internal (Control Key -PP01)-4 HRS

When i do scheduling the system should propose the start and finsh date by considering the Planned Deliver time .

Thanks in Advance .