Hi All ,
I have External processing Operation in my routing and i have maintained the control key as PP02 and Mainatined the Plannned Deliver time for that operation , But when i do production order scheduling system is not considering the Planned Delivery time , How to make the system to consider the Planned Delivery time in production Order scheduling .
Example :\
production order:0001
Operation 0010
- Internal (Control Key -PP01)
4 HRS
operation 0020
internal (Control Key -PP01)
- 4 HRS
operation 0030
External((Control Key -PP02)
10 DAYS
Operation 0040 --- Internal (Control Key -PP01)-4 HRS
When i do scheduling the system should propose the start and finsh date by considering the Planned Deliver time .
Thanks in Advance .
Regards,
Kumar