Hi Expert,

I need your clarification if my current scenario is correct:

In the product location, we plan it manually using product heuristic:

Product Heuristic: SAP_PP_002

PP Plng Procedure: Manual Without Check

Procedure: lot-for-lot

Safety Stock Method: MZ

Safety days: 10

Procurement type: F

The result of the product heuristics only generates the purchase requisition if the stock level falls to 0 or the actual days of supply falls to 1 day and it only generate lot-for-lot result. Is product heuristics doesnt consider safety days in its planning? Is SNP heuristics the only way to have the planning generate the correct result?

Thanks

Lhon