hi i have schedule a process chain and solved meanwhile errors and made the load success up to target,but whenever the error occurs the status of log view of that process chain turns red color as all of us know ,even after successful completion by overcoming all the problems up to target,still the status of the process chain in log view is in red color ,why? whats the error ,please tell me

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

this error is related to a system table, in which the status of one of the process remains red. So the chain is red for the system.

You can check it following these steps:

1. Open the messages of a failed step by right clicking on it and selecting 'Display Messages'.

2. In the opened popup click on the tab 'Chainu2019. In a parallel session go to transaction se16 for table rspcprocesslog and display the entries with the following Selections:

- Copy the variant from the popup to the variante of table rspcprocesslog

- Copy the instance from the popup to the instance of table rspcprocesslog

- Copy the start date from the popup to the batch date of table rspcprocesslog

- Press F8 to display the entries of table rspcprocesslog.

Check in the status field. If it is R, it means that this process is considered red for the system and all chain is red for this.

Hope it helps.

Best regards.

Simone.

Former Member
0 Kudos

thanks

Answers (1)

Answers (1)

jaigupta
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi kumar,

The status of the process chain will be red as it got failed once,no need to worry in that case as you have resolved all the errors and loaded the data successfully...

However you can manually change the status,for that follow the below link:

http://www.ittestpapers.com/blogs/how-to-change-process-chain-%28pc%29-status-in-sap-bw.html

regards,

jai