Jan 17, 2012 at 08:14 PM

Dates and times in APO

170 Views

Hi All

I am getting bit messed up with different dates and times in R/3 and APO. Could you please provide me some details on the relation and where these dates and times are maintained in APO and R/3

1. Transit Time:

Is it Total Replenishment time, Planned Delivery Time

Is it maintained in Purchase Infor Record or Transportation lane

2. Material Availability Date

Can PPDS works on MAD or only on Delivery Requirement date (as in RRP3)

3. Does PPDS Considers

Goods Issue Time, Goods Receipt time, Load Time / Pick Pack time for scheduling the order or for total duration of the order. As in DS it can show if the order can be on time or delayed with respect to delivery time! (in Network view of DS) so it considering the transit time and all other time maintained!

Please let me know how to straighten these things out!

Thank you in advance