We are on SRM7.01 with ECC 6.0 EHP 4.
This is in reference to Plan Driven Procurement.
Issue : Any Change in PR is subjected to release stratergy but on change only "without release" data transferring to SRM.
Changes like " Qty, Delivery date" etc made in PR and went for release but without considering release status changes went to SRM.
This is not the case for Fresh PR , In this case any PR subjected to release will go to SRM only after complete release.
Any Event linkage i am missing ?
Any note is availaible ?
Whats the standard behaviour ?
Advice from your side will be highly appreciated.