Former Member
Jan 16, 2012 at 02:09 PM

MRP Planning

40 Views

Hi,

We have an issue where the part created the purchase requistion and gets rescheduled daily and thus the Release date in the purchase requistion gets Changed daily.As of result of which, the PR is not falling within a varint which is used to convert PR into PO.

Part is not used in any BOM and there are no open orders or sales orders for this part. MRP considered this part and created a PR as the safety stock has been consumed. Now whenever MRP runs(MRP runs daily), the requirement date gets Changed automatically, though there is no entry observed in planning file.Backward scheduling is applied in this case.

Your thoughts on this issue is appreciated!

MRP type for the part is PD - MRP

Safety stock is in negative

Planning mode 1 - Adapt Planning data (Normal) in MD03.

Planning file entry - no MRP planning type is checked

let me know if I am missing anything!