Hi Gurus,
Our net requirement calculation is considering Under delivery tolerance sourcing from Sales requirement, this is working fine in the net requirement calculation but we would also require to similarly consider the Sales tolerance as tolerated material shortage in MTS procurement planning, for example:
Sales order (S1) is requesting finished product P1 for 891 Kg on February, 01st, with a tolerance of -/+ 10%
Receipt (R1) is covering S1with 891 Kg as receipt qty
R1 has a dependant requirement on material P2 for 891 Kg
P2 is configured in a Make To Stock strategy.
Available stock (AS) on P2 is 850 Kg
Stock replenishment order (R2) with 1500 Kg planned on March, 1st
Actual procurement planning is pegging (AS) and (R2) on (R1) dependant requirement, leading then to have R1 with a planned start date on March, 1st (corresponding to latest pst), resulting into a delay covering customer requirement!
We would expext as a result of the procurement planning of above example to get (R1) dependant requirement only peg on (AS) as 850 Kg is within S1 tolerance.
Is there a way to achieve this ?