Hi all
I want to schedule a simple prev maint based on running hour.
I am giving initial reading through meas document and giving an annual estimate.
system will give me some scheduled calls on the basis of cycle time.
But in this case the equipment is not running continuously so the system given scheduled dates will vary from the actual running hours.
My client is not interested in manual entry of meas doc all the time. They have PLC/SCADA panel where they can see the running hour. Client will not be happy to see huge mismatching of actual reading on scheduled call date by system.
I need this single cycle running hour counter based maint to be mapped with discontinued operation.
Any input is highly appreciated.
Thanks