I would like your help with the following questions.

1. Which table and which field do I need in order to see the time (in days) that passed from the moment I order goods until the goods were received.

2. Which table and which field do I need in order to see the dates that goods movement were performed for each material that is defined in the system.

Thanks.

Moderator message: Please use better subjects

Edited by: Jürgen L. on Jan 15, 2012 12:06 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jan 15, 2012 at 06:32 PM

    Hi Kobish,

    You can also use the standard reports:

    WPDTC for the lead time ("from the moment I order goods until the goods were received")

    MB51 for material movements ("the dates that goods movement were performed for each material")

    If you want to use the tables mentioned before, I suggest the fields

    PO Date EKKO-BEDAT

    Delivery date EKBE-BUDAT, where EKBE-BWART = 101 (note that there can theoretically be several receipts for the same PO item - several 101's)

    All material movements (not just receipts) MKPF-BUDAT or if you want to have the material number, the plant, the qty and the date in the same table, use the database view WB2_V_MKPF_MSEG2.

    BR

    Raf

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 15, 2012 at 09:25 AM

    Hi,

    1. Which table and which field do I need in order to see the time (in days) that passed from the moment I order goods until the goods were received.

    try following

    Po creation date table EKKO

    Delivery date in po Table EKPO

    Goods receipt date table MKPF

    2. Which table and which field do I need in order to see the dates that goods movement were performed for each material that is defined in the system.

    table MKPF

    Regards

    Kailas Ugale

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 15, 2012 at 02:20 PM

    Hi Kobish,

    1. PO delivery date in EKPO

    PO schedule lines in EKET

    Use PO history table EKBE to take the posting date/document date of the material document.

    2. The goods movement details of any material can be found from MSEG table (mvt type and material) and put the material document no and year in MKPF table to get the posting date/document date.

    Hope it helps

    sBk

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.