Hi All,
Iam facing an issue with partial commitement of quantity for a production order with missing parts.
Here is my scenario
I need to produce 1 FG.
Following are the raw materials in the BOM
Raw1 - 10
Raw2 -10
Raw3 -10
I create an order for 1 FG. and following is the stock situation during availabilty check on release
Raw1 - 05
Raw2 -10
Raw3 -05
When i release the order and save it, i find that committed quantity for all the components is zero.
I need to have setting where it should diisplay the available stock as the commited quantity as shown below
Raw1 - 05
Raw2 -10
Raw3 -05
In short it should allow partial commitment of the components, I have already checked the partial commitment option in production scheduling profile but still it is not working. Please provide your inputs.
Regards,
Raj
.