Hi All,

Iam facing an issue with partial commitement of quantity for a production order with missing parts.

Here is my scenario

I need to produce 1 FG.

Following are the raw materials in the BOM

Raw1 - 10

Raw2 -10

Raw3 -10

I create an order for 1 FG. and following is the stock situation during availabilty check on release

Raw1 - 05

Raw2 -10

Raw3 -05

When i release the order and save it, i find that committed quantity for all the components is zero.

I need to have setting where it should diisplay the available stock as the commited quantity as shown below

Raw1 - 05

Raw2 -10

Raw3 -05

In short it should allow partial commitment of the components, I have already checked the partial commitment option in production scheduling profile but still it is not working. Please provide your inputs.