Hi Gurus help please...
My requirement is to change the confirmed qty to allocate that qty to other sales order.
The scenario is as below.
It is multilevel assembly process under MTO. We work on different sales order (different material and quantity) same time. For each sales order there are corresponding production orders for each work center. In initial level we assemble certain material say X which can be used either for Sales order A or sales order B.
Even though it is planned to use item X manufactured and quantity confirmed under sales order A only for final assembly for A, it is alternatively used for A and B.
Since this decision is taken just before Final assembly time to time, we need to change the confirmed quantity allocated to one sales order to another each time.
Is there any provision for backward integration so that, Corresponding to the quantity confirmation done in final assembly , The quantity is auto adjusted in initial level of assembly?
For example: We certify X 10 numbers under A and 5 numbers under B purchase order. But we utilize 10 for B and 5 for A in final assembly.
How to make changes in confirmed quantity of initial assembly. ( certain cases it is serial number parts, in some other cases, it is having just material number and quantity.)
Is ther any solution under COGI,COHV or is to be addressed by BAPI