I have a question on component quantities in a BOM. Can a BOM calculate the demand and then round up to the nearest multiple of a predetermined amount for an individual component?
Example :
Parent A - Qty 1_
Component B - qty 1
Component C u2013 qty 2
Component D u2013 qty 4
If I have an order for 10 Au2019s and component D comes in multiples of 12, but is setup as each, can the BOM produce a requirement for 48 instead of 40? If so, would this be setup in the BOM or Material Master for the component? Also parent A has fluctuating demand and component D is used in multiple parent items.
Any help would be greatly appreciated.