Hi All,
I have come across a requirement. The details are,
1. Inspection plans created with MICs having control indicators as Complete copy model, required characteristic, sampling procedure required and single result recording.
2. The requirement is to change all MICs control indicators to u201Csummerisedu201D. Rest all parameters (other control indicators and tolerance values, selected sets, units of measurement and decimals should remain unaffected)
I tried using CWBQM. Unfortunately I couldnu2019t find the provision to do this in CWBQM.
I tried QS27. Later realised system doesnu2019t allow to replace MICs with complete copy model.
Is there any way by means of which I can execute this in mass, as there are around 50K records.
Thanks in advance
Regards,
Anand Rao