Hi all,
We have a situation where the PR is showing the incorrectiong processing status. The user creates a PR from planned order. If the current price is not sure RFQs are sent. After sendign rfq teh PR processing status changes to RFQ. When quote is recieved, user may or maynot update the quote in ME47.
After this th PR is converted to PO. The problem happens is that PR still has status as "RFQ created". The status does not change to "PO created".
Please let me know what could be issue. Thanks.
Regards
AF.