Former Member
Jan 12, 2012 at 08:32 PM

CO and Process order without material using T. Code CORO

306 Views

Hi

We need to use Process Order without material functionality for recording "changeover" time and cost (i.e. setting up process for production of other material in a production line).

For this purpose we have configured a separate process order type. We have created a separate activity for Changeover and planned rates using KP26.

Now we create Process Order without material using T. Code CORO and confirm it using COR6N. On confirmation system successfully credits Cost Center.

We need to know:

1) whether we should settle the process order as well or no need to assign settlement profile to Order Type

2) Or should we run Cost Estimate first.

Plz help, if any have idea