Hi,
Planned order creation via MRP depends, If we change Delivery date in Stock transfer Order.
I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
MRP profile details :
Plnd delivery time 1
GR processing time 1
Planning time fence 38
Tot. repl. lead time 38
Can you please let me know why system is beaving in this manner?
Regards
Utsav