Dear Guru's,

I am running MTO scenario for a plant. Maintained strategy group for finished product as 20 & for raw materials as 70. The indiv / collective requirement for FG is 2 & for RM is 1. As per standards, the stock for raw materials should be under particular sales order which means system should not consider plant stock.After running MRP throgh MD50, Purchase requistion got generated for raw materials, But, when converting the planned order to production order for finished product, system is giving message as " All materials are available". As system should not consider plant stock, it should raise PR for RM which later will be converted to PO & when the material is received, GR will be done & the stock will be visible under sales order stock. My question is As when the PR for the RM is generated, why is system giving message as " All materials are available" ?

Request you to provide the inputs.

Thanks in advance.