Skip to Content
0
Former Member
Jan 11, 2012 at 05:15 PM

How to modify SORDEROR data in the ICHDFC1 data matrix ?

19 Views

Hi,

I am currently working to display the key figure corresponding to the confirmed PO in the Order Forecast Monitor.

In the Time Serie DFC01 (OFM), this Key Figure is named SORDEROR.

I can display it successfully but I also want to modify the datas displayed.

In standard, the key figure displays the quantities at the corresponding delivery date, but I would like to change this date and to add the GR Processing Time (from the GR/GI view of the /SAPAPO/MAT1).

What I would like to display is :

new date = delivery date + GR processing time.

For now I am thinking about :

Creating a new service for the Data Matrix ICHDFC1.

Create a new method related to this service in order to calculate the new date

Apply this service to the SORDEROR key figure in the data matrix

But I don't know if such a solution is possible ?

Is there another way (may be more simple 😊 ) to modify the displayed date ? Is there a way to modify this by the customizing ?

Regards

Vincent