Procurement type

816 Views

hi

Need some information on using procurement type X on the finished goods. We have scenario where plant A makes the product and also procures the product from Plant B if the demand is high.

1) Is it necessary to use the split valuation if we use the procurement type X on the material master?

2) Can we use standard valuation or do we need to user moving average?

3) How does the procurement type X affect the product costing? Currently in our company, we use either E or F procurement types for the finished goods (everything is standard valuation) and product costing calculates the standard costs from the components or transfers the cost from producing facility in the case of procurement.

4) Any impacts on repetitive manufacturing?

Thank you