Hi
we have a finish material ,which can be manufactured using 3 different work centers.Then I create 3 production versions to link each work center .
PV1 Routing 1(work center1) BOM 1 production line:work center1
PV2 Routing 1(work center2) BOM 1 production line:work center2
PV3 Routing 1(work center3) BOM 1 production line:work center3
Is it possible to create a batch job to dispatch planned order between work centers in CM40?I am able to manually dispatch planned orders between different work centers in CM22..
CM40 use the same selection/strategy profile as CM22 and the planned orders are dispatched to other period if current period get overload..But I expect CM40 to dispatch the planned orders to other available work centers..Anyone has any suggestions?
thanks very much..
Edited by: Monst Yang on Jan 10, 2012 9:59 PM