on 01-10-2012 8:33 AM
Hi,
In MD04, for some line items MRP element came blank. We have rectified the problem. After running MRP, still the line item with MRP element is blank is not getting removed. Kindly suggest how to remove.
I have seen some of them have faced MRP element data was blank but for me its MRP element.
Regards / US
do mdo1
go to md04
click on the lens. in the small window that open click on the pencil. delete
if pencil icon is not coming probably you wont be able to delete it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Is this blank element a sales order or delivery? This is possibly the issue described by note 70408.
By the way, I have created a WIKI about the most common inconsistencies on transaction MD04.
You may access it on the link below:
http://wiki.sdn.sap.com/wiki/x/uwSUDw
Check the section "Sales order/delivery number is not displayed" for more details.
BR
Caetano
Hi Caetano,
Thanks for your mail. I saw your wiki link, its really good job.
For a particular sales order if we run MRP then in MD04 (Second column - MRP element) we should see CusSt, CusOrd and Pl Ord but now system is displaying CustSt and one more line with blank mrp element.
Eg:
30.11.2011 CustSt 0050000689/001100/0000
30.11.2011 0050000689/1100
Where 50000689 is sales order and 1100 is sales order line item.
Now I want to remove the line item which is having blank MRP element.
Kindly let me know any SAP note is available?
Regards / US
Hi,
Yes we are using MTO, blank planning element is in black.
We found the reason why we got this blank planning element. Initially in material master MRP 4 view we maintained collective requirements. After changing to individual requirement, system was giving requirement properly. Now we are trying to remove the unnecessary requirement from the system. But we cant able to remove.
Any solutions to remove the inconsistent data?
Regards / US
US,
Sounds like you created the sales order during the period of time when the material master was incorrect. There is still something inconsistent in the Sales order itself that you have not corrected yet.
Easiest way to re-determine the updated material master data and pull it into the sales order is to go into the sales order item in VA02; remove the plant, press enter, then re-insert the plant, press enter again, then save.
Best Regards,
DB49
Hi DB49,
You are correct, ours is MTO scenario. In material master MRP 4 view, initially user has used collective requirement (2). due to this system gave MRP element as BLANK and it was not giving requirement. After changing to individual requirement (1) system gives requirement properly. Now the issue is when I am trying to remove the mrp element which is blank. I could not.
In VA02, plant filed is non editable mode. Is there is any other way to remove the blank mrp element?
Regards / US
hi
why not try MD01 with NEUPL ?I doubt some material not change at all..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.