Skip to Content
0
Former Member
Jan 09, 2012 at 06:28 PM

Error during MAIN_NEWBAS/STARTSAP_NBAS

530 Views

Hello,

We are upgrading from 4.7 to ECC 6.0 EHP 5 and we are getting an error on phase MAIN_NEWBAS/STARTSAP_NBAS.

Checks after phase MAIN_NEWBAS/STARTSAP_NBAS were negative!

Last error code set: RFC call to subst_get_uvers failed with key RFC_ERROR_COMMUNICATION (open): SAP_CMINIT3 : rc=20 > Connect to SAP gateway failed Connect_PM GWHOST=ocean71, GWSERV=sapgw00, SYSNR=00 LOCATION CPIC (TCP/IP) on local host with Unicode ERROR partner '10.100.100.71:3300' not reached TIME Mon Jan 9 12:00:18 2012 RELEASE 720 COMPONENT NI (network interface) VERSION 40 RC -10 MODULE nixxi.cpp LINE 2898 DETAIL NiPConnect: 10.100.100.71:3300 SYSTEM CALL connect ERRNO 79 ERRNO TEXT Connection refused COUNTER 866 System start failed Earlier, validating the profile failed, see INSTANCE.OUT

In the phases.log I see the following

2WETQ372 test RFC failed, rc="-1"

2 ETQ370 starting test RFC

4 ETQ359 RFC Login to: System="DEV", Nr="00", GwHost="ocean71", GwService="sapgw

00"

4 ETQ359 RFC Login to: System="DEV", Nr="00", GwHost="ocean71", GwService="sapgw

00"

2 ETQ231 RFC Login failed

4 ETQ359 RFC Login to: System="DEV", Nr="00", GwHost="ocean71", GwService="sapgw

00"

2 ETQ231 RFC Login failed

2WETQ372 test RFC failed, rc="-1"

2EETQ354 Starting system failed, rc="0"

4 ETQ010 Date & Time: 20120109120018

Any help is appreciated.

Thanks

Scott