Hi,

I am using 8.81 and using the procurement wizard to create back to back purchase orders from the sales order.

I have brought in the delivery date field to the rows in step 3, but unlike the other fields you are unable to change it.Therefore you have to go to the final stage, create the purchase order and then go back in to it and change the dates which is not as effective,

Does anyone know how I can change the delivery date?

Sam Burchell