Issue related to CO03

Former Member
0 Kudos

Hi SAP Experts,

I have a issue related to CO03. In CO03 (Goto->costs->analysis), I am getting total amount 17790.03. In that 5162.00 as coded material and 12628.03 is non coded material. Means Report is displaying 12628.03 amount in Actual column and it is not displaying anything cost Elements column. If we double click on 12628.03 total details will disply.

But I want to display all line items in this CO03 (Goto->costs->analysis). It is displying in CO03 (Goto->costs->Itamization). But user is asking in CO03 (Goto->costs->analysis) only.

I need to do any configuration settings related to this?

If you need more information, can you please reply to this forum.

Thanks in advance.

Ranjith

Accepted Solutions (0)

Answers (1)

Answers (1)

srinivasa_maruvada
Active Contributor
0 Kudos

Check settings of your Cost component structure at OKTZ.

Create and Assign a new CCS to Assignment Organiz units- Cost component structure

Company code/plant/costing variant

Srinivas

Former Member
0 Kudos

Hi Srinivas,

What you have mentioned in your mail, those settings are there in OKTZ.

Thanks,

Ranjith

Former Member
0 Kudos

Hi,

Can you please help me on this issue?

Thanks,

Ranjith Patil