Skip to Content
0
Former Member
Jan 06, 2012 at 10:24 AM

Goods issue

12 Views

Experts,

I have posted stock for material 123456 on 06.01.2012 ,with movement type 561.

In sales order VA02 ,Schedule lines ,shipping tab Delivery date is 06.01.2012 ,Goods issue date is 07.01.2012,Loading date is 07.01.2012,Material avail.date is 07.01.2012,Transportation Plan. Date is 07.01.2012.

when I am doing delivery with 06.01.201 sysytem is showing the error" No schedule lines due for delivery up to the selected date"

If I am doing delivery with 07.01.2012 system is allowing to create delivery.

Please help me solve the issue and please tell me why the Goods issue date is changed to 07.01.2012.

Regards'

Kiran

Edited by: kirang1 on Jan 6, 2012 11:25 AM