Net price not getting updated in EKPO and EINE table

Former Member
0 Kudos

Hello All,

I have an issue with the Net price.

Net price is updated correctly in Scheduling Agreement and Info records. But it is not updated in EKPO and EINE tables.

EKPO and EINE tables are taking last year's values.

I have checked Item conditions, MAterial master data ACcounting view. In accounting view Moving average price and standard price is maintained . Please let me know how it affects Net price if any.

Please guide what else needs to be consider.

Thanks in advance,

Forum Shah

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for helping.

JL23
Active Contributor
0 Kudos

EINE table is part of info record.

EINE table gets the price updated if you create a conditon that is valid today.

But if you create a price condition that is valid for the future, then the EINE price is not updated.

You can run RM06INP0 report to update the EINE price from the current valid condition.

However this EINE price update will not effect your PO price, the PO price is determined directly from the conditions.

but do you create POs in reference to schedule agreements? Don't you just create schedules with ME38?

Former Member
0 Kudos

Hello,

Scheduling agreement is created. I dont know with refrence to what it is created. The only issue here is Net price mentioned in SA is not getting updated in EKPO and EINE.

Please let me know what should be done to update EKPO table.,

Thanks,

Forum

JL23
Active Contributor
0 Kudos

why do you think that the schedule aggreement price has to go flow the info record?

the info record price is for standard business, special agreements have their own prices.

when you create a PO from a PR, then you decide what source you assign e.g. in ME57.

there you select EITHER an info record, or an outline agreement.

so the price is either coming from info record, or from outline agreement.

but the outline agreement price is a special price for a certain period based on a certain quantity.the price in the info record is a general price for a certain period, not based on a total quantity.

Former Member
0 Kudos

Hello Jürgen L. ,

It solved my issue. I ran the report for "Price determination for Scheduling Agreemnt".

Thanks for helping.

Forum Shah