I have both Plant Maintenance orders and Production orders.
Plant Maintenance order - takes place every monday morning.
Production order - needs 5 days of work at the work center to be maintained.
I would like to dispatch the production order such that the 5 days of production work can be broken up before and after the maintenace order, with breaks for the maintenance work.
I noticed that I was able to do with some overall profiles.
With some overall profile, the whole 5 days of production order will either be dispatched before or after the maintenace order, not just pausing during the maintenance.
Which profile affects this setting - control, selection, time, evalutation, etc???