Former Member
Jan 06, 2012 at 03:12 AM

CM25 capacity leveling profile

188 Views

dear all...

I have both Plant Maintenance orders and Production orders.

Plant Maintenance order - takes place every monday morning.

Production order - needs 5 days of work at the work center to be maintained.

I would like to dispatch the production order such that the 5 days of production work can be broken up before and after the maintenace order, with breaks for the maintenance work.

I noticed that I was able to do with some overall profiles.

With some overall profile, the whole 5 days of production order will either be dispatched before or after the maintenace order, not just pausing during the maintenance.

Which profile affects this setting - control, selection, time, evalutation, etc???

THANKS!!