There is one critical problem arises related to commitment budget during PR and PO. Please go through the below scenario:-

Suppose I have released budget of Rs. 5000 in one WBS and I create one PR of value 3000. Now my commitment is Rs. 3000 and available budget is Rs. 2000. Now suppose I delete this PR. Now my commitment should be zero but the system is showing commitment of Rs. -3000 and available budget is Rs. 5000. Now again I create a PR of Rs. 3000 in the same WBS. Now my commitment should be Rs. 3000 but system is showing commitment is zero and allow me to create PR for another Rs. 5000. But in real sense I consumed budget of Rs. 8000 but my release budget is Rs. 5000.