Skip to Content
0
Former Member
Jan 05, 2012 at 05:58 AM

Detailed Scheduling calculating In Correct time

700 Views

Hi,

I have an issue where the MRP is showing incorrect Start Time and End Time for Operations in Detailed scheduling i.e. The Start and End time for FERT and HALB Planned Orders are the same.

Scenario:

BOM:

1 FERT requires 1 HALB

1 HALB requires 1 ROH

Routing

60 EA of FERT is Produced in 1 Hour

60 EA of HALB is Produced in 1 Hour

We are using Strategy 10 and I have entered a PIR for 60 Pieces so logically

- HALB order should start at say 09:00 AM and end at 10:00 AM

- FERT order should start at 10:00 AM and end at 11:00 AM

however in Detailed scheduling tab of Planned Order, the system shows the Order start time for both as 9:00 AM against the first operation 0010 in both HALB and FERT.

In Basic Production dates of Planned Orders its showing the end time as 17:00 for both HALB and FERT.

Can someone please explain to me why this is happening? We are not using overlapping or anything of the sort and I have checked my Master Data and couldn't find anything wrong with it.

Regards,

Hashim Abbasi