Hello,
My inspection lot says status as CRTD.
I have checked the task list validity and inspection plan validity. Its fine.
i have mentioned all sampling procedures also.
Cataloge are also there.
Sampling procedure is also ticked in control indicator.
And when i assign click sample calc. it says "No sampling procedure found for sample determination" in QA02.
Also i have checked material master it contains the inspection type and no manual procedure is ticked.
Please provide a solution to me.
Thanks & Regards,
Alok Tiwari