Target Cost in Process Order not calculated

Hello,

In Process order, after deliver of FG the target cost is not getting calculated,

Could you please help me why the target cost is not calculated in process order.

I have configured all setting for WIP and Variance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    Jan 04, 2012 at 10:29 AM

    Check at OKTZ whether CostComponent Structure is activated or not

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      please check the timings of standard cost estimation and settlement.after the settlement, there is no use of running standard cost estimation and calculation of target cost.

      So, as per your comments on above, reverse the settlement and rerun the variance and settlement once again.

      Best Regards

      Nagaraju SSV

  • avatar image
    Former Member
    Jan 04, 2012 at 04:24 PM

    hi

    target cost will be updated only after calculating variance. it does not calculate after delivery of finished goods, calculate variance the target cost will be updated

    krishna

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 04, 2012 at 04:57 PM

    Target cost fields in the report at process order will be updated after calculation of Variance at KKS2..

    Till such time no values will be updated. Check whether you ran KKS2 or not with production order status as Teco.

    Srinivas

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 05, 2012 at 01:36 PM

    Hi,

    Target costs are only calculated after goods movements have occured on the order, the Target Costs are then calculated during the Variance calculation.

    Target costs will only be calculated after the first goods receipt has been posted to the order. Also you have to ensure that the information to calculate target costs exists on the system in particular in OKV6.

    This estimation is based on the customizing for the Target cost version in transaction OKV6 as in turn will the "real" calculation of the Target costs via the variance calculation.

    So in OKV6 the Target cost will be based on preliminary costing on the order, an alternative cost estimate or the current standard cost estimate. Importantly if the choosen option is not fulfilled e.g. no current standard cost estimate, the target costs will not be predicted or calculated.

    regards

    Waman

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 05, 2012 at 01:46 PM

    Hi,

    [1] Kindly check the validity of your standard cost estimate and date of your process order.

    [2] Check the Variance Key in material master data (MM03) under costing 1 tab, there should be Z00001 inputted in the field.

    Rosniev