Hi All,

I have create Multiple Counter plan with cycle set sequence 1,2 ..

Please find the details :-

Cycle set sequence 1 -600KM,4Month ,given counter for 600KM ..

Cycle set sequence 2 -1200KM ,8Month,given counter for 1200KM both the counters for 600 &1200 KM are same ..

Now relation i have given as OR ..

My counter last reading was on 30.12.2011 & Value is 500KM

I started the Plan on 30.12.2011

My Annual Estimate for Counter is 3650 , hence my activity shows as 10KM per day ..

Scheduling period is 999Day ..

Now when i schedule the Plan in IP10 with OR relation , date as 30.12.2011

I am getting the below as my Call dates :-

15.01.2012 Cycle Set sequence 1 New start Hold

14.05.2012 Cycle Set sequence 2 Scheduled Hold

13.07.2012 Cycle Set sequence 1 Scheduled Hold

From above i am not clear as how system gave 15.01.2012 ..? i was expecting call on 10th or 9th of Jan 2012 as my

Current counter reading is 500KM and 600KM will be covered in next 10days as per annual estimate ..

Please help me out ..

regards

giri