Hi All,

I am having few queries with the above subject.

My customer is asking that he will assign persons(from HR) to the work centers. and based on the assignments done he want some functionality like

1. At the time of operation confirmation through CO11N in the person field only assigned persons(in Work center) should be available

2. At the time of capacity availability check system should check the person attached to work center only. e. g. suppose two persons for 8 hrs are assigned to work center then if order need 18 labor hours, in this case system should tell that capacity is not available. and then if third person added to Work center master then it will tell capacity is available.

Now my question is :

Whether above requirements are possible? if yes then please please tell me how to do?\