Hi ,

after execution of the mrp system is not generating subcontracting pr's for some of the materials which are at last hierarichal structure of the BOM .

Example :

For Finished goods material 8000-0105-white , the BOM is maintained with semi finished material FFK-CL364-SFF-42S

and again tht semi finished material contains the BOM of other semi finished material FGK-CL364-SFF-21S and again this material contains the BOM of raw material YF-ELASTAIN-0040s.

Now when i run the mrp for header material system is generating the requirement for only FFK-CL364-SFF-42S . its not considering other two material . Please advice

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jan 03, 2012 at 11:40 AM

    have you maintained the MRP relavent data for all the materials? if so what is the mrp type maintained?

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 03, 2012 at 11:44 AM

    Hi,

    Maintain all MRP relevent data and re-run MRP. Also check if stock is there for those material if it is there it will not do so.

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 07, 2012 at 11:10 AM

    solved

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.