Former Member
Dec 29, 2011 at 02:27 PM

System should not consider Cus Req Del date in sales order during MRP run

214 Views

Hi Guru,

Please let me know if there way so that System should not consider Cus Req Del date in sales order line for material planning while running MRP for NON STOCK items. But it should consider contractual lead time for generating PR.

This will generate Purchase Requisition on very next day of Sales Order booking and hence material will be available before cust req del date which can be dispatched to customer on required date.

Hence, there will be no risk of inventory also since there is firmed demand against this PO.

Thanks,

Om